Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Uganda expressway connection; construction due to start
    September 25, 2019
    Construction work is due to start on the expressway project connecting Busega with Mpigi in Uganda. The contract was awarded to the Chinese construction firms China Civil Engineering Construction Corporation (CCECC) and China Railway 19th Bureau Group Company Limited. The companies have established a joint venture partnership to handle the work. The project is costing around US$147 million and the 24km expressway should take around three years to build. A loan from the African Development Bank is helping to
  • India mulls feasibility of bridge over Palk Straight to Sri Lanka
    October 27, 2015
    India will carry out a feasibility study on a road link between Rameswaram in Tamil Nadu state and Thalaimannar in Sri Lanka, a federal government minister has said. "It needs the consent of both countries,” said Union minister of state for road transport, highways and shipping, Pon Radhakrishnan. “The project needs to be discussed at various levels," according to a brief report by India’s Hindu newspaper. Radhakrishnan told the reporters that federal government had begun consultations to carry out a
  • Italy’s giant Messina Strait bridge
    October 2, 2024
    Report being published for Italy’s giant Messina Strait bridge
  • Norway moves toward more E39 coastal road improvements
    April 4, 2019
    Norway is working on plans to make more of the major north-south E39 coastal route a ferry-free highway, coasting €35.3 billion, according to media. In Norway, the trans-European route 39 is part national road system and is developed and maintained by the public roads administration. It runs for 1,330km along the coast from Klett just south of Trondheim to Nørresundby. Norway’s E39 is mostly a two-lane undivided road with only relatively short sections near Stavanger, Trondheim and Bergen being motorw