Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • We can be Heroes
    January 11, 2023
    Paraguay’s Puente Héroes del Chaco will provide a vital transport link for the country once it is complete, Mauro Nogarin and Mike Woof report
  • Chile’s capital Santiago’s key tunnel project
    October 24, 2017
    Chile’s capital Santiago now looks set to benefit from a new road tunnel link, which will cost up to US$900 million to construct. The Americo Vespucio Oriente I (AVO I) will stretch 9km through the city and will include a tunnel section. The project has been the focal point for discussions between the local authorities as well as the companies OHL and Sacyr.
  • Road repairs planned for Nampula in Mozamique
    December 17, 2014
    In Mozambique a budget of US$100 million has been set for road rehabilitation work to be carried out in Nampula Province. The upgrades will be carried out for a total distance of a 300km and will be carried out in phases. Work will commence in 2015. The road improvements will be carried out on the Nametil-Nampula city, Moma-Nametil city, Angoche-Moma, Monapo-Angoche and Angoche-Nametil sections of road.
  • Mexican road projects in hand while others face delays
    February 23, 2012
    Several key highway developments are being planned in Mexico, although project delays are now facing increasing public scrutiny.