Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Chilean bridge project achieves resolution
    February 26, 2020
    A resolution has been achieved for Chile’s Chiloe Island bridge project.
  • Chile’s major bridge construction project
    April 25, 2017
    Planning work for Chile’s Chacao Bridge project is underway at present. The new suspension bridge will provide a link to Chiloe Island and will be the longest structure of its type in Latin America when complete. Because of the risk of major earthquakes in the area, the bridge has to be constructed to cope with substantial shocks. The project is being handled by the Consorcio Puente Chacao consortium and has been in the design phase since February 2014. Chile’s Ministry for Public Works wants to ensure that
  • Hyundai looking for new partner for Chilean bridge deal
    March 21, 2016
    South Korean firm Hyundai is looking for a new partner to join the consortium that will construct Chile’s Chacao Bridge. The project has been planned for some years, having been cancelled once previously, and will connect with Chiloe Island, replacing the current ferry service. The new partner for the consortium would take the place of Brazilian firm OAS, which is currently embroiled in legal difficulties due to an ongoing investigation in Brazil. The aim is that a new partner could buy out the 49% stake in
  • Chile’s key bridge project for Chacao Crossing
    September 27, 2017
    Chile’s landmark Chacao Bridge project could be ready for traffic by mid-2021, according to the Ministry of Public Works. The 2.76km suspension bridge will connect the Chilean mainland with Chiloe Island, replacing the current ferry service and helping to develop the local economy. The project is costing around US$700 million. The cranes that will be used to install the main sections of the bridge will arrive on site shortly. A new schedule for the project will be announced early in 2018.