Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Chile-Argentina tunnel project progress
    October 20, 2017
    Further progress is being made with the landmark Agua Negra Tunnel project that will connect Argentina and Chile. The new tunnel will run through the Andes mountain range, providing an improved highway link between the two nations, boosting trade and transport. The consortia pre-qualified for the tender process will be announced during November 2017.
  • Questions and delays afflict some key Indonesian transport project
    March 28, 2014
    Indonesia’s transport expansion programme is seeing new projects commence, but others afflicted by questions over feasibility and delays. Questions over the economic feasibility of the proposed Sunda Strait Bridge project have been raised by the Public Works Ministry. This mega-project is intended to provide a road link between Sumatra and Java. But construction of the 30km structure could cost up to US$23 billion and might not be fully recovered, even if the investor collects toll fees under a 100-year con
  • Taking the coast road on Reunion Island
    April 4, 2017
    An ambitious project on Reunion Island will improve transport
  • Taiwan bridge link project moving ahead
    February 23, 2017
    Construction of the Kinmen Bridge in Taiwan has now been resumed, with work having restarted on the project in late 2016. The bridge will be 5.4km long in all and will have a 1.05km long main section, connecting the islands of Greater Kinmen and Little Kinmen (also known as Lieyu). The project includes building approach roads for the bridge as well as cuttings and connecting ramps. Costing US$292 million and with funding being provided jointly by Taiwan’s Government and the local authorities, the bridge is