Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Strong interest in building new Chile-Argentina tunnel link
    October 30, 2013
    Interest is strong in the proposed tunnel linking Chile and Argentina. Some 37 companies have shown expressions of interest in the US$1 billion Agua Negra road tunnel. This includes 22 consortia and includes Latin American firms such as Panedile, Techint, Camargo Correa, Jose Cartellone. It also includes the Chinese firms China Railway Construction Corporation, China Railway Bureau Group, China State Construction Engineering Corporation and Sinohydro Group. Daewoo, Hyundai Engineering and SK Eng & Construct
  • British Columbia decides on Massey Tunnel
    August 20, 2021
    Canada’s Pacific coast province of British Columbia has announced the George Massey Tunnel replacement will be another tunnel and not a bridge as decided earlier.
  • Delays for new bridge linking Brazil and Paraguay
    June 4, 2014
    Construction work on a new bridge connecting Brazil and Paraguay has suffered a further delay. The 760m suspension bridge itself is expected to cost in the order of US$102 million while the building of link roads and customs/immigration facilities bring the project total to some $170 million, according to a report by Business News Americas. Contractor Empresa Sul Americana de Montagens (EMSA) was originally thought to be the front runner for the project following its lowest cost bid of $101.78 million for t
  • Scotland’s new Queensferry Crossing over the Forth Estuary
    December 23, 2015
    The new Queensferry Crossing under construction in Scotland will be the third landmark bridge spanning the Forth Estuary - Mike Woof writes When the new Queensferry Crossing over the Forth Estuary opens at the end of 2016, it will be the third landmark bridge to be built spanning this short stretch of water. Lying alongside the existing road bridge and the historic rail bridge, this new structure will be as groundbreaking as the two earlier crossings were at the time of their construction.