Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Delay for tenders on key Colombian highways
    April 28, 2014
    The tender process has been extended for three highway concession packages in Colombia, according to Business News Americas. The country's national infrastructure agency (ANI) has extended the bid deadlines for the Pacífico 2 (Bolombolo-La Pintada), Pacífico 3 (La Pintada-La Virginia) and Río Magdalena 2 (Remedios-Puerto Berrío) projects. The three highway concessions are worth a total of US$1.2 billion and form part of Colombia’s Autopistas para la Prosperidad highway programme. ANI opted to delay the tend
  • Malaysian roads break ground
    January 27, 2025
    Work is underway for key Malaysian roads.
  • The Lessons of the Genoa bridge collapse
    April 23, 2019
    The partial collapse of the Polcevera viaduct, better known as the Morandi Bridge, has prompted debate regarding the technical and administrative aspects of maintaining road infrastructures. We discussed it with the engineer Gabriele Camomilla, former Director of Research and Maintenance of the Società Autostrade, who coordinated the only major structural intervention performed on the bridge, carried out in the early 1990s
  • Florida replacing Howard Frankland Bridge
    August 22, 2018
    Florida Department of Transportation (FDOT) is working on plans to replace the Howard Franklin Bridge. The project is now expected to cost US$814 million, an increase from the $750 million originally envisaged. The contract is expected to be awarded in 2019, with construction commencing in 2020. The first stage of the project should be ready for use in 2024, providing a significant increase in daily capacity and boosting the emergency evacuation capacity also. The new bridge will carry four lanes of traffi