Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Paraguay’s planned highway projects
    January 22, 2019
    Several major road projects are underway in Paraguay at present, though issues are afflicting some. Although the Rute del Este consortium comprising Sacyr, Mota Engil and Ocho A was awarded the PPP contract to upgrade Ruta 2 and Ruta 7, the necessary funding has yet to be delivered. The Inter-American Development Bank (IADB) and the US Bank have both said that they would give the necessary funding. A new deadline has been set for the funds to be delivered at the end of March 2019. Meanwhile there are also d
  • New route for Chilean capital
    July 8, 2013
    Chile’s congested capital Santiago is set to benefit from the construction of a key route that will help reduce journey times and improve traffic flow, particularly at peak periods. The tender process will open shortly for the Americo Vespucio Oriente (AVO) highway in Santiago, a 9.3km highway connection that will include the construction of a tunnel under the San Cristobal area.
  • Hyundai Heavy Industries posts optimistic results
    July 7, 2014
    Equipment manufacturer Hyundai Heavy Industries has published optimistic results in the financial report for its construction equipment operations. The firm’s Annual Report 2013 said that the global construction market slowed in 2013 as economic uncertainty in the US and Europe continued and China maintained its tight credit policies to keep growth in check. In emerging markets such as the Middle East, Brazil, Russia, and Africa, falling international raw materials prices combined with a market slump in th
  • Costa Rica road project delay
    November 29, 2024
    A key Costa Rica road project faces delays and questions.