Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Vital structures
    February 10, 2012
    A wide variety of products are available to help bridge owners reduce the need for costly repairs. Bridges are one of the most expensive structures on a highway system, and their maintenance, and where necessary, repair will save millions over time. Prevention being better than cure means that anything that can be done to reduce the need for repair is a good investment. For example, a MOOG bucket-type inspection unit has been commissioned for the Naini Bridge in Allahabad in the state of Uttar Pradesh, Indi
  • Self-climbing formwork solution for bridge pylons
    February 27, 2012
    Harsco Infrastructure has provided self-climbing formwork (SCF), which is helping ensure quick and safe access during the construction of a 320m tall pylon for the world’s longest cable-stayed bridge.
  • Vietnam’s key highway project feasibility study
    March 9, 2018
    The feasibility study is being handled for a stretch of Vietnam’s North-South highway project. The project is likely to cost US$5.22 billion, of which $2.8 billion will be provided by private funding sources, with the remainder coming from the Vietnamese Government’s sources. The project is being overseen by Vietnam’s Ministry of Transport. Vietnam’s Department of Public-Private Partnership (PPP) Projects has urged the bodies involved with eight PPP sub-projects to complete feasibility studies for these
  • Delayed Houston Ship Canal Bridge nearing first phase
    February 23, 2024
    The delayed Houston Ship Canal Bridge is nearing its first phase completion.