Delays ahead for Slovakia’s Visnove tunnel

Slovakia's transport ministry says the 7.5km Visnove tunnel near Zilina, part of the D1 motorway, will be delayed by two years to open in 2022. The recent announcement came as the ministry agreed to an extension to the construction permit held by Salini Impregilo for work on the twin-tube tunnel. The design-and-build contract worth about €410 million was assigned to the Salini Impregilo-led joint venture DUHA in 2014 by the National Highway Company NDS.
September 5, 2018 Read time: 1 min
Slovakia's transport ministry says the 7.5km Visnove tunnel near Zilina, part of the D1 motorway, will be delayed by two years to open in 2022.


The recent announcement came as the ministry agreed to an extension to the construction permit held by 7809 Salini Impregilo for work on the twin-tube tunnel.

The design-and-build contract worth about €410 million was assigned to the Salini Impregilo-led joint venture DUHA in 2014 by the National Highway Company 5891 NDS.

The highway runs past Lietavská Lúčka, Višňové and Dubná Skala in the Žilina region of northern Slovakia.

The tunnel is also part of Corridor 5 of the Trans-European Networks -TEN - which links Bratislava in Slovakia with Uzhhorod in Ukraine. It is financed by the Slovak government and the European Union through the European Investment Bank.

For more information on companies in this article

Related Content

  • Slovakia tunnel sections underway but some delays
    January 23, 2018
    The route for new tunnel links for Slovakia’s D1 highway has been agreed. New tunnels now look set to be built on the 13.5km stretch between Turany and Hubova section of the D1 highway. This plan calls for the construction of the Korbelka and Havran tunnels at an estimated cost of €900 million. Building these two links would bypass the Lower Fatra mountain range, with the Korbelka Tunnel measuring 5.9km and the Havran Tunnel measuring 2.9km long. The Slovak Environment Ministry rejected an appeal against th
  • Date set to complete D1 Višňové Tunnel section
    July 20, 2023
    The D1 section between Lietavská Lúčka and Dubná Skala in Slovakia includes the partially completed 7.5km twin-tube Višňové Tunnel - to be the country's longest.
  • Duha and Salini Impregilo to build Slovakia D1 motorway stretch
    April 23, 2014
    Slovak national motorway company NDS has chosen the consortium consisting of fellow Slovak construction company Duha and Salini Impregilo of Italy as the winner of the public procurement tender to build a 13km stretch of the D1 motorway. The Lietavska Lucka-Visnove-Dubna Skala stretch of Slovakia’s D1 includes the 7.5km long Visnove tunnel and is a tender worth nearly €410 million. It is expected that Skanska and Doprastav, which were excluded from the competition, will appeal against NDS' tender award dec
  • Slovakia tunnel excavation complete
    September 21, 2018
    Excavation work on Slovakia’s Visnove Tunnel has now been completed. Driving the tunnel took nine months longer than originally anticipated. The 7.5km tunnel will be Europe’s seventh longest when complete and forms part of the D1 highway between Dubna Skala and Lietavska. Work on this highway started in 2014, with the construction being carried out jointly by Italian contractor Salini Impregilo and local firm Duha. Fitting out of the tunnel is now commencing, with equipment such as ventilation and traffic