Czech bypass project faces delay

An important Czech bypass project is facing delays.
By MJ Woof September 18, 2020 Read time: 1 min
An important bypass project in the Czech Republic is now facing delays - image © courtesy of Artof Sha, Dreamstime.com
Delays are now affecting construction work for the Czech Republic’s Ceske Budejovice bypass project. As a result, the bypass will not be ready for traffic until 2024.

Geological problems in the Pohurka Tunnel are at the heart of the delays. Dealing with unexpectedly high levels of groundwater will add around €3.88 million to the project. In all, the project is costing around 204.9 million.

Related Content

  • Improved Czech road safety
    January 6, 2025
    The Czech Republic has seen road safety gains.
  • Unexpected problems delay Swiss highway project
    November 28, 2012
    A highway project looks set to face extended delays in its construction due to the discovery of contaminated land. A two year highway project planned in the canton Valais will now take considerably longer to complete due to the unexpected discovery of mercury contamination on the site. The contamination is historic and appears to be the result of disposal carried out by a local chemicals firm in the 1930s, when there were few controls over what could be dumped. The company had tipped its chemical waste into
  • Russian road works planned
    January 31, 2022
    A major programme of Russian road works is being planned.
  • Chilean bridge project to Chiloe Island delayed
    October 31, 2018
    Delays to the project to construct Chile’s Chacao Bridge mean that an additional two years may be required for the work. The work is now being carried out solely by a consortium, Consorcio Puente Chacao, headed by the South Korean contractor Hyundai.