Czech bypass project faces delay

An important Czech bypass project is facing delays.
By MJ Woof September 18, 2020 Read time: 1 min
An important bypass project in the Czech Republic is now facing delays - image © courtesy of Artof Sha, Dreamstime.com
Delays are now affecting construction work for the Czech Republic’s Ceske Budejovice bypass project. As a result, the bypass will not be ready for traffic until 2024.

Geological problems in the Pohurka Tunnel are at the heart of the delays. Dealing with unexpectedly high levels of groundwater will add around €3.88 million to the project. In all, the project is costing around 204.9 million.

Related Content

  • Czech road plans call for major construction
    January 31, 2018
    The Czech Republic is setting out its programme to develop its road infrastructure network. The plans call for work to build 360km of roads and highways as well as maintaining existing stretches. The construction plans include work on the Prerov section of the D1 highway, a stretch of the D40 from Hulin to Frystak, the Hodejovice section of the D3 highway and the Frydek-Mistek by-pass. They also include work to two sections each of the D35 highway and D11 highway as well as a number of bypasses for the D6
  • New Zealand highway proposed
    June 15, 2021
    A potentially controversial tolled highway project has been proposed for New Zealand's South Island.
  • Sweden appoints Veidekke Anläggning to Förbifart Stockholm work
    May 2, 2019
    Sweden’s transport administration Trafikverket has appointed Veidekke Anläggning as a temporary contractor for work on the Lovön section of the Stockholm Bypass - Förbifart Stockholm. The deal is worth around €9.6 million. The contractor will take over work started by a tender winner whose contract has been cancelled, according to Swedish media. It is expected the new contractor will be on site until the end of the year, by which time Trafikverket says it hopes to have re-tendered the remaining work.
  • Costa Rica capital bypass
    February 26, 2021
    Costa Rica’s capital bypass is close to completion.