Czech bypass project faces delay

An important Czech bypass project is facing delays.
By MJ Woof September 18, 2020 Read time: 1 min
An important bypass project in the Czech Republic is now facing delays - image © courtesy of Artof Sha, Dreamstime.com
Delays are now affecting construction work for the Czech Republic’s Ceske Budejovice bypass project. As a result, the bypass will not be ready for traffic until 2024.

Geological problems in the Pohurka Tunnel are at the heart of the delays. Dealing with unexpectedly high levels of groundwater will add around €3.88 million to the project. In all, the project is costing around 204.9 million.

Related Content

  • Lincoln bypass project in the UK approved
    April 15, 2022
    The Lincoln bypass project in the UK has been approved.
  • Legal dispute delays Stockholm project
    March 1, 2012
    A legal dispute continues to delay work on Stockholm's Bypass project.
  • Russian road project faces delay
    June 19, 2019
    Russia’s Sochi highway project will not now be completed by 2024. The original plan was to build a 119.km new route to replace the existing A147 route that connects Dzhubga with Sochi. Because of the challenging terrain, this project to build a new four lane highway without the twists and turns of the existing route would have been extremely costly, with a pricetag of as much as US$18 billion. However the project has now been downgraded as being of a lesser priority than other Russian road projects ongoing
  • Major infrastructure upgrades in Czech Republic
    May 8, 2012
    Upgrade work to five sections of the D1 highway in the Czech Republic is due to commence in spring 2012. The first sections to be rebuilt are from are Sternov-Psare, Loket-Horice, Vetrny Jenikov-Jihlava, Lhotka-Velka Bites and Velka Bites-Devet Krizu. The Transport Ministry prioritised these sections for repair, although full permission has yet to be given before the work can commence.