Czech bypass project faces delay

An important Czech bypass project is facing delays.
By MJ Woof September 18, 2020 Read time: 1 min
An important bypass project in the Czech Republic is now facing delays - image © courtesy of Artof Sha, Dreamstime.com
Delays are now affecting construction work for the Czech Republic’s Ceske Budejovice bypass project. As a result, the bypass will not be ready for traffic until 2024.

Geological problems in the Pohurka Tunnel are at the heart of the delays. Dealing with unexpectedly high levels of groundwater will add around €3.88 million to the project. In all, the project is costing around 204.9 million.

Related Content

  • North Germany bypass project faces delay
    November 9, 2017
    Construction delays are holding up the opening of a new bypass in northern Germany that will connect the towns of Löhne and Bad Oeynhausen. Construction work on the link commenced in 2008 and has so far cost some €170 million. In all the project is expected to cost €208 million to complete. Although the vast majority of the work has been carried out on the new bypass some finishing works remain to be completed.
  • Czech highway funding secured
    May 10, 2021
    Funding has been secured for a major Czech highway.
  • Delays have hit the Czech Blanka Tunnel
    December 12, 2013
    Further delays are adding to the sorry tale of woe surrounding the construction of the Blanka Tunnel project in the Czech Republic. The tunnel was supposed to improve connectivity and reduce traffic congestion in Czech capital Prague. However following a series of disagreements over the work being carried out as well as the spiralling cost, financing, legal problems and various technical issues, the construction of the tunnel has finally ground to a halt. Czech construction firm Metrostav has said that it w
  • Czech road project, bidding delay
    May 22, 2023
    Bidding has been delayed for a major Czech road project.