An important Czech bypass project is facing delays.
      
  
                       
                By MJ Woof
            
            
                          
                September 18, 2020
              
            
                          
                Read time: 1 min
              
                    
                 
    Delays are now affecting construction work for the Czech Republic’s Ceske Budejovice bypass project. As a result, the bypass will not be ready for traffic until 2024.
Geological problems in the Pohurka Tunnel are at the heart of the delays. Dealing with unexpectedly high levels of groundwater will add around €3.88 million to the project. In all, the project is costing around 204.9 million.
 
     
         
         
         
        