Croatia rejects complaints over Peljeski Bridge tender

Croatia’s public procurement body has rejected complaints by all three international consortia over a winning low tender for the Peljeski bridge. Bids for construction of the four-lane 2.4km bridge were submitted in the middle of last year. The bridge will connect Croatian territory by traversing the Adriatic Sea’s Mali Ston Bay. Vehicles must currently head from Croatia into Bosnia to re-enter a peninsula that is Croatian territory. Croatia’s State Commission for Control of Public Ordering Processes
April 6, 2018 Read time: 2 mins

Croatia’s public procurement body has rejected complaints by all three international consortia over a winning low tender for the Peljeski bridge.

Bids for construction of the four-lane 2.4km bridge were submitted in the middle of last year. The bridge will connect Croatian territory by traversing the Adriatic Sea’s Mali Ston Bay. Vehicles must currently head from Croatia into Bosnia to re-enter a peninsula that is Croatian territory.

Croatia’s State Commission for Control of Public Ordering Processes  - DKOM – said there were no grounds for retendering the contract. Two consortia submitted their complaints to DKOM in January only days after similar action by another consortia led by the Austrian firm 945 Strabag.

The Turkish and Italian consortium tendered bids around €343 million Strabag offered around €349 million. But China Road and Bridges Corporation came in at around €208 million.

DKOM said there was no violation of procurement rules by the successful bidder, China Road and Bridge, and that no issues related to the bidding price.

DKOM also noted that any issues over bidders submitting unsustainably low prices in order to win work was an issue for the European Commission that handle complaints over dumping pricing.

While the bridge will be good for the economy of the Croatian area, Bosnia and Herzegovina has in the past requested that Croatia pause procurement for the project pending discussions between the two countries over the design.

Bosnia’s concern is that the largest ocean-going ships should have access up Ston Bay to Bosnia’s only sea port, Neum, should the Bosnian government decide to upgrade the terminals there.

Discussions have resulted in Croatia accepting design changes – and added costs - suggested by Bosnia, including an increase of bridge's height from 35m to 55m and spacing bridge supports at least 200m apart.

Project completion was originally set for 2022.

In June, the European Commission approved €357 million of the European Union’s Cohesion Policy funds to build the bridge – around 85% of the project’s cost. The European Union is also funding supporting infrastructure, such as access roads, including tunnels, bridges and viaducts, the building of an 8km bypass near the town of Ston and upgrading works on the existing road D414.

For more information on companies in this article

Related Content

  • Turkish win for Romanian Sibiu-Pitesti section
    March 10, 2022
    Mapa Insaat and Cengiz Insaat Sanayi will build the the 31km between Boita and Cornetu.
  • Strabag and GBS-Infrastructure to build Sofia-Kalotina motorway
    August 2, 2018
    Austrian construction firm Strabag and Bulgarian firm GBS-Infrastructure Construction have won the contract to build the 32.4 km Sofia-Kalotina motorway. Cost of the 32.4kmn four-lane project is estimated at €120 million with completion set for 2020. The Kalotina motorway will run from the capital Sofia’s ring road to the border town of Kalotina where it will connect with Serbia’s A4 motorway. It is also part of 6,100km 10-country European route E80 running from the Portuguese capital Lisbon to the
  • Czech tender interest from international companies
    December 13, 2012
    The tender process for upgrade works on the D1 highway in the Czech Republic is attracting international bidding. The five sections of highway are worth €173.2 million in all, with investments of €59 million planned for 2012. Companies entering bids so far include Metrostav, Skanska, Strabag, Eurovia CS, Swietelsky Stavebni, OHL ZS, Dalnicni Stavby Praha. Bidders also include several consortia including one comprising M-Silnice, Bogl a Krysl and Berger Bohemia and one made up of Hochtief CZ and Silnice Casl
  • Consorcio Panama Cuarto Puente wins fourth Panama bridge contract
    August 1, 2018
    Panama has decided to award a contract for the design and construction of a fourth bridge over the Panama Canal to Consorcio Panama Cuarto Puente. China Communications Construction Company and its subsidiary China Harbour Engineering Company are heading up the consortium for the US$1.42 billion project. Other consortia that put in bids included Dragados Sucursal Panamá and Astaldi-Daelim. News agencies report that the government initially chose the Chinese consortium in June but the final award was