Cost increases for major Chilean highway project

The cost of Chile’s Vespucio Oriente highway project is increasing, while its completion also looks set to be delayed. A 13% budget increase is now required due to additional costs from a number of factors such as urban landscaping, according to Business News Americas. The Américo Vespucio Oriente (AVO) expressway is being built in Chilean capital Santiago and was originally expected to cost in the region of US$940 million. However Chile’s Public Works Ministry, MOP, has said that the route will now cost so
November 15, 2013 Read time: 3 mins
The cost of Chile’s Vespucio Oriente highway project is increasing, while its completion also looks set to be delayed. A 13% budget increase is now required due to additional costs from a number of factors such as urban landscaping, according to Business News Americas. The Américo Vespucio Oriente (AVO) expressway is being built in Chilean capital Santiago and was originally expected to cost in the region of US$940 million. However Chile’s Public Works Ministry, MOP, has said that the route will now cost some $1.06 billion. The project is for a 40-year concession package that includes building and operating a 9.3km underground expressway through Santiago. The route runs from El Salto Avenue to Príncipe de Gales Avenue, under the existing Américo Vespucio beltway. Because of the route, the project will be both complex and challenging and MOP also said that firms or joint ventures interested in participating in the tender will now have until December 30th 2013 to submit technical bids, compared to the previous deadline of November 22nd 2013. The ministry will then announce the economic proposals for the concession on January 20th 2014.

The new AVO route will be built on two levels, each one carrying a one-way, three-lane expressway. Road capacity will increase to 8,000 vehicles/hour. The project is required as Santiago suffers chronic congestion, particularly at peak periods. The authorities split the long-delayed AVO tender in two, given the complexity of the project, which will run through five municipalities in eastern Santiago. The new AVO route will provide the missing link in the city's beltway and was originally intended to run underground for 13km, joining El Salto with Grecia Avenue. However, this plan attracted strong protests from residents of the La Reina and Peñalolén districts. The 968 Chilean Government opted to split the project and call a tender only for the first 9.3km stretch. However in March 2014 Chile will have a new election and responsibility for the project will then be passed to whichever party wins. Opposition candidate for the presidency, Michelle Bachelet, has previously said she opposed the splitting of the tender and this could further add to the wrangling over the project, as well as adding additional delays.

For more information on companies in this article

Related Content

  • Colombian concession contracts cause concern
    June 13, 2014
    A report from insurance firm AIG warns that up to half of Colombia's 4G highway concessions could face financial hurdles due to over-estimated predictions of traffic flows. Colombia is at present putting out to tender its fourth generation (4G) concessions, which involve some US$25 billion in investment, reports Business News America. This investment is impressive and is Latin America's biggest move to expand and improve road infrastructure. But while many companies have shown interest and were prequalified
  • Europe extends engine emissions deadline
    July 16, 2020
    Europe is extending the engine emissions deadline.
  • Increasing costs of highways project delays
    May 15, 2012
    Costs are climbing for Catalonia’s Eix de la Conreria highway project in Spain. The B-500 project is now expected to cost €400 million, a jump of €30 million from the previous estimate made just six months ago. The new link will connect Barcelona with Baix Maresme and Valles and the start of work on the project is also now expected to be delayed until 2012. The project requires the construction of four lanes with two running in either direction and is at present in the design and environmental assessment s
  • Windsor & Maidenhead starts £114.8 million highways competition
    May 5, 2025
    The seven-year maintenance contract covers 632km of roads as well as footways and bridges throughout the English borough just west of London.