Cost increases for major Chilean highway project

The cost of Chile’s Vespucio Oriente highway project is increasing, while its completion also looks set to be delayed. A 13% budget increase is now required due to additional costs from a number of factors such as urban landscaping, according to Business News Americas. The Américo Vespucio Oriente (AVO) expressway is being built in Chilean capital Santiago and was originally expected to cost in the region of US$940 million. However Chile’s Public Works Ministry, MOP, has said that the route will now cost so
November 15, 2013 Read time: 3 mins
The cost of Chile’s Vespucio Oriente highway project is increasing, while its completion also looks set to be delayed. A 13% budget increase is now required due to additional costs from a number of factors such as urban landscaping, according to Business News Americas. The Américo Vespucio Oriente (AVO) expressway is being built in Chilean capital Santiago and was originally expected to cost in the region of US$940 million. However Chile’s Public Works Ministry, MOP, has said that the route will now cost some $1.06 billion. The project is for a 40-year concession package that includes building and operating a 9.3km underground expressway through Santiago. The route runs from El Salto Avenue to Príncipe de Gales Avenue, under the existing Américo Vespucio beltway. Because of the route, the project will be both complex and challenging and MOP also said that firms or joint ventures interested in participating in the tender will now have until December 30th 2013 to submit technical bids, compared to the previous deadline of November 22nd 2013. The ministry will then announce the economic proposals for the concession on January 20th 2014.

The new AVO route will be built on two levels, each one carrying a one-way, three-lane expressway. Road capacity will increase to 8,000 vehicles/hour. The project is required as Santiago suffers chronic congestion, particularly at peak periods. The authorities split the long-delayed AVO tender in two, given the complexity of the project, which will run through five municipalities in eastern Santiago. The new AVO route will provide the missing link in the city's beltway and was originally intended to run underground for 13km, joining El Salto with Grecia Avenue. However, this plan attracted strong protests from residents of the La Reina and Peñalolén districts. The 968 Chilean Government opted to split the project and call a tender only for the first 9.3km stretch. However in March 2014 Chile will have a new election and responsibility for the project will then be passed to whichever party wins. Opposition candidate for the presidency, Michelle Bachelet, has previously said she opposed the splitting of the tender and this could further add to the wrangling over the project, as well as adding additional delays.

For more information on companies in this article

Related Content

  • New road tunnels for Chile’s capital
    October 21, 2021
    New road tunnels are being planned for Chile’s capital, Santiago.
  • Serbia’s pan-European Corridor X is in the slow lane
    October 23, 2017
    It’s been slow progress on Serbia’s Corridor X project. Gordon Feller reports. Back in the early 2000’s, the European Union undertook an ambitious programme to link the main cities of its south-eastern region. This involved connecting five key seaports – the Greek cities of Patras, Igoumenitsa, Piraeus and Thessaloniki as well as Romania’s Black Sea city of Constanta. Initially the plan involved two motorways across Greece. The first was a new 780km route including a branch to Ormenio on Greece’s north-eas
  • Delay for tender for link roads to Istanbul’s new Bosporus bridge
    June 25, 2015
    The tender process for the road connections to the third bridge over the Bosporus in Turkey has been delayed once more. This is the third time the tender for the connecting roads for Istanbul's third bridge over the Bosporus has been postponed. The tender for the North Marmara Motorway was originally set for 6th March 2015 but was then pushed back to the 6th May. It was then announced that the tender would be run in two stages, with the Kinali-Odayeri motorway tender on 7th July and the Kurtkoy-Akyazi motor
  • Consultation soon for Vancouver area’s Massey Tunnel replacement
    September 19, 2019
    The Canadian province of British Columbia could put options for a Massey Tunnel replacement out to consultation late this year or early next. A statement from the BC ministry of transportation and infrastructure said the government is in discussions with various stakeholders about which options it will put out for consultation. Whatever option is chosen to replace the ageing four-lane Massey Tunnel – be it a bridge or another tunnel – it will be will be either six or eight lanes, according to the gove