Contractors competing Colombian construction concessions

The tender process is underway for the third section of Colombia’s Pacific route connecting La Pintada and La Felisa. This route forms part of the Autopistas de la Prosperidad project between Medellin and Buenaventura. The 231km section includes 26 bridges and three tunnels and will cost some US$621.4 million to construct. All three sections plus the Magdalena and Norte highway will be awarded by July 2014 with works due to begin in 2015. The highway stretches should all be finished in 2020. For the first s
May 13, 2014 Read time: 2 mins
The tender process is underway for the third section of Colombia’s Pacific route connecting La Pintada and La Felisa. This route forms part of the Autopistas de la Prosperidad project between Medellin and Buenaventura. The 231km section includes 26 bridges and three tunnels and will cost some US$621.4 million to construct. All three sections plus the Magdalena and Norte highway will be awarded by July 2014 with works due to begin in 2015. The highway stretches should all be finished in 2020. For the first section of the Pacific route, the bidders were Autopistas Conexion Pacifico 1 (Episol and other firms) and Infraestructura Vial para Colombia. For the second section of the same route, there was only one bidder, PSF Concesion La Pintada. Meanwhile Mincivil and Colpatria have submitted Colombia's first private road project to the Ministry of Finance for its approval. The project consists of a double-lane road between Ibague and Cajamarca that will cost $684.6 million and the project will not require any public funding.

Related Content

  • Colombian highway connection being built
    March 27, 2019
    Construction work is well underway for Colombia’s Autopista Mar 1 motorway project. The route is due for completion in 2022, connecting the country’s Caribbean and Pacific coasts through Medellin. The project includes construction of the Tunel de Occidente. A finance package worth US$713 million in the shape of loans from eight banks is helping fund the project. Work is also ongoing for the Conexio Norte routelinking Remedios with Caucasia. This project should be complete by 2021. Meanwhile the Via del Nu
  • Key highway project in Colombia faces delay
    December 2, 2013
    Work on a key stretch of Colombia’s Ruta del Sol highway project is behind schedule, with the route now unlikely to open to traffic before 2017. The 21.6km section of the highway facing these delays will link Villeta and Guaduas in Cundinamarca. A key challenge is technical as the US engineering firm Gall Zeidler Consultants has warned Colombia’s infrastructure agency (ANI) that this section of the route is geologically unstable. The proposed route could be at risk from slippage and will need to be stabilis
  • Consortium Via al Puerto to finish Colombia’s Buga-Buevantura road
    May 24, 2016
    Colombia’s National Infrastructure Agency (ANI) has approved Consorcio Estructura Plural Via al Puerto to build the remaining 26.5km of the Buga-Buenaventura dual carriageway. Construction costs will be just under US$358 million with another $645 million likely needed to maintain and operate the public-private partnership road for 30 years. Works include construction of two tunnels, 12 bridges, 7.5km of cycle lanes, as well as maintenance of 111km of the main road, according to a report by El Pais new
  • Consortia compete for Colombian construction and concession contract
    June 4, 2014
    Colombia's US$561 million Perimetral de Oriente de Cundinamarca4G highway concession package has received bids from four different consortia. Business News Amercas reports that this is the highest number of bidders that a 4G highway concession has received since the country’s national infrastructure agency, ANI, started receiving bids in April for its first wave of nine highway concessions. There were comparatively few bidders for the first three projects so ANI made a number of changes, including revising