The completion of work on Colombia’s troubled tunnel project is now finally in sight. A new contractor will be selected by Colombia's National Road Institute (Invias) to complete the last section of work required on the La Linea Tunnel. The winner of the tender process will be announced on 13th June 2017. An additional US$50 million is being budgeted by the Colombian authorities to complete the work. It is expected that in all, finishing the project will cost $86.6 million. Work still to be carried out incl
April 26, 2017 Read time: 2 mins
The completion of work on Colombia’s troubled tunnel project is now finally in sight. A new contractor will be selected by Colombia's National Road Institute (2812 Invias) to complete the last section of work required on the La Linea Tunnel. The winner of the tender process will be announced on 13th June 2017. An additional US$50 million is being budgeted by the Colombian authorities to complete the work. It is expected that in all, finishing the project will cost $86.6 million. Work still to be carried out includes tackling the geological problems along 1km of the main tunnel stretch as well as completing lining works on 2.8km of this section. Also remaining to be carried out are paving for 5.5km of roads and completing work on four small bridges in the approaches to the tunnel.


The project has had a somewhat torturous history, with numerous delays during its construction due to a series of different problems ranging from difficult geological conditions to the wrong kind of insurance cover. The construction firm Constructora Carlos Collins had previously been working on the project lost its contract when it failed to meet the deadline in 2016.

For more information on companies in this article

Related Content

  • Colombia’s key tunnel – completion date set?
    January 11, 2019
    Colombia has set a new date for the completion of the La Linea tunnel project of May 2020. The project has been subject to a series of delays due to issues such as insufficient financing, unexpected geological problems and even the wrong type of insurance cover. The completion date for the main tunnel stretch has been moved back several times, but it is hoped that it will finally be completed on the date, which was announced by Colombia’s president, Ivan Duque. The completion of the entire project, whic
  • Colombia sets out major strategy for highway investment
    January 19, 2015
    International interest is strong in Colombia’s infrastructure expansion. Five foreign firms are competing in the country’s 4G road tender process. Fomento de Construcciones y Contratas (FCC), Sinohydro, Sacyr, Tradeco and ICA are amongst the companies competing for 10 contracts worth some US$5.88 billion. The first project opening for tender on 19th May 2015 will be for the Puerta de Hierro-Carreto-Palmar de Varela and Carreto-Cruz del Viso routes. The final tender documents for the 10 projects are being pu
  • Colombia road projects delivered
    September 24, 2020
    Important road projects in Colombia have been delivered successfully.
  • Colombia continues tunnel plans
    February 17, 2012
    With work on Colombia's first La Linea tunnel still incomplete, discussions are now being held regarding plans for the second tunnel.