Colombian tunnel project progress

A key Colombian tunnel project is seeing progress.
By MJ Woof August 31, 2020 Read time: 1 min
Progress is being seen in Colombia for the Tunel de Occidente project - image © courtesy of Wollertz, Dreamstime.com

An important road tunnel project in Colombia is seeing progress being achieved. Driving work for the second tube of the Tunel de Occidente project has been completed, some two months ahead of schedule.

Around 497,400m3 of material has been removed from the tunnel drives since excavation commenced in September 2018. The Tunel de Occidente features twin parallel tubes, each with a length of 4.6km. The tunnel forms part of the Autopista al Mar 1 road project, linking Medellin with Santa Fe.

The tunnel is being built by the concessionaire Desarrollo Vial al Mar (Devimar).

Related Content

  • Launch soon for the Sunderland Bridge’s deck across the Wear
    March 24, 2017
    The team constructing the New Wear Crossing near the English city of Sunderland is preparing for the final launch of the 300m bridge deck. In recent weeks, the legs of the 100m-tall centrepiece have been secured to the foundations within the riverbed and most of the rigging used to raise it into place has been removed. While the bridge deck was being painted, the bottoms of both pylon legs were filled with 175tonnes of concrete, The next major process will be to slowly pull the bridge deck out acr
  • Project building new Biobio bridge in Chile on track
    August 28, 2014
    Construction work on the fourth bridge spanning Chile’s Biobio Bridge is proceeding on schedule. The project site is located in Chile’s Gran Concepcion area. Construction could commence in 2016, with completion expected in 2018. Environmental studies have yet to be completed however. The work will be carried out as part of a concession package and the bridge is expected to cost some US$214 million to construct, carrying two lanes for vehicle traffic as well as claiming pedestrian and cycling connectivity. T
  • Key projects free up Auckland's congested motorway network
    June 14, 2012
    A number of key projects in Auckland, New Zealand will free-up the city’s congested motorway network - Mary Searle reports.Auckland is a sprawling city, home to 1.4 million people, one third of New Zealand’s total population. Until recently, greater Auckland comprised Auckland city, North Shore city over the harbour bridge to the north, Waitakere city to the west and Manukau city to the south. An amalgamation of these various cities’ councils, plus the regional council and three district councils into one,
  • Far from formulaic
    January 4, 2013
    Formwork solutions for the first axial suspension cable stayed bridge in India; and a four-lane road bridge in Germany’s Harz Mountains, are among the latest bridge-based formwork projects analysed by Guy Woodford. RMD Kwikform India has won the contract to design and supply shoring and formwork solutions for the first axial suspension cable stayed bridge ever built in India. The Kota Bridge’s innovative design sees a single 350m span cross the entire width of the Chambal River, with three approach spans on