Colombian tunnel project progress

A key Colombian tunnel project is seeing progress.
By MJ Woof August 31, 2020 Read time: 1 min
Progress is being seen in Colombia for the Tunel de Occidente project - image © courtesy of Wollertz, Dreamstime.com

An important road tunnel project in Colombia is seeing progress being achieved. Driving work for the second tube of the Tunel de Occidente project has been completed, some two months ahead of schedule.

Around 497,400m3 of material has been removed from the tunnel drives since excavation commenced in September 2018. The Tunel de Occidente features twin parallel tubes, each with a length of 4.6km. The tunnel forms part of the Autopista al Mar 1 road project, linking Medellin with Santa Fe.

The tunnel is being built by the concessionaire Desarrollo Vial al Mar (Devimar).

Related Content

  • Delay possible for Chile-Argentina tunnel project
    May 10, 2018
    Delays may be a possibility for the construction of the Agua Negra Tunnel, which will run through the Andes mountain range and connect Argentina and Chile. The tendering process is being held back while further geological studies are carried out. An analysis of the initial geological work carried out so far for the project has highlighted a number of discrepancies with the information gathered. It is known that there are three main fault lines cutting across the intended tunnel route however. The tunnel
  • Colombia tunnel project conclusion plan
    December 6, 2016
    Tendering is commencing for the final portion of works to complete Colombia’s La Linea tunnel project. Around 12% of the work on the tunnel still has to be completed, with the work expected to cost US$68.5 million. The tender is being carried out by Colombia's National Road Institute (Invias). The tunnel project has been delayed for a series of reasons. Colombian contractor Constructora Carlos Collins was constructing the tunnel but did not meet the necessary deadline. As a result, Invias opted to open the
  • Colombia road plan includes new project
    February 26, 2018
    Colombia's future 4G road programme now includes a new project, to provide a new link from Popayan to Santander de Quilichao. The three month consultation process has been completed and the steps needed for an environmental license to be awarded are now underway. Should all continue to go to plan, construction of the 77km link should commence in August 2018, although a target for the completion date has yet to be announced.
  • Tunnel essential to reduce congestion
    February 21, 2012
    Vietnam's Ho Chi Minh City's dense population, which was estimated to be 10,680 persons/km2 in 2005, is, over the next ten years, set to benefit from the completion of the Thu Thiem Urban Area project, which will provide homes for up to 200,000 people.