Colombian tunnel project progress

A key Colombian tunnel project is seeing progress.
By MJ Woof August 31, 2020 Read time: 1 min
Progress is being seen in Colombia for the Tunel de Occidente project - image © courtesy of Wollertz, Dreamstime.com

An important road tunnel project in Colombia is seeing progress being achieved. Driving work for the second tube of the Tunel de Occidente project has been completed, some two months ahead of schedule.

Around 497,400m3 of material has been removed from the tunnel drives since excavation commenced in September 2018. The Tunel de Occidente features twin parallel tubes, each with a length of 4.6km. The tunnel forms part of the Autopista al Mar 1 road project, linking Medellin with Santa Fe.

The tunnel is being built by the concessionaire Desarrollo Vial al Mar (Devimar).

Related Content

  • Projects planned for Colombia’s highway connections
    March 10, 2014
    From Colombia comes news of a US$13.4 billion funding package that will be directed towards the construction of nine highway projects. This package of works includes construction and concessions for a series of highways, which will be carried out under the PPP model. These include the Conexión Norte, Autopista al Río Magdalena 1, Autopista al Río Magdalena 2, Autopista al Mar 1 and Autopista al Mar 2. They also include the Autopista Conexión Pacífico 1, Autopista Conexión Pacífico 2 and Autopista Conexión P
  • Colombia: Estructura Plural SAC 4G is awarded motorway concession
    July 2, 2015
    Estructura Plural SAC 4G has been awarded the motorway concession Autopista Mar 1 in Colombia. The 176km road between Fernando Gomez Martinez Tunnel will run across San Jeronimo and Santafe, reaching Canasgordas. The project will cost US$565.12 million and have 41 bridges and 17 tunnels. The existing road will be improved and a second lane added between Medellin and Santa Fe. Meanwhile, Colombian construction firm Construcciones El Condor and the national infrastructure agency ANI have signed a pu
  • Colombian tunnel drive nearing completion
    October 14, 2019
    The excavation work for the new La Quiebra road tunnel link in Colombia is close to completion. The drive is being carried out from both ends of the tunnel and should meet by November 2019. The tunnel construction work will then include completing the lining, building the roadway and carrying out fitting out work. The 8.4km tunnel is costing around US$170 million to build and should be complete by December 2020. The tunnel will form part of the Vias del Nus 4G highway connecting the country’s second city, M
  • Brazil Tamoio highway and São Sebastião tunnel work
    July 5, 2016
    Brazil’s Tamoio Highway and São Sebastião tunnel construction is of major importance – Mauro Nogarin reports. The modernisation and expansion of Brazil’s Tamoio highway is a major project for Brazil. The project has an estimated cost of $1.5 billion and work on the first section from Planalto was completed in January 2014, costing around $350 million. The project is being managed by the state-owned agency DERSA, which deals with road development. According to the concessionaire for the Tamoios highway p