Colombian tunnel project progress

A key Colombian tunnel project is seeing progress.
By MJ Woof August 31, 2020 Read time: 1 min
Progress is being seen in Colombia for the Tunel de Occidente project - image © courtesy of Wollertz, Dreamstime.com

An important road tunnel project in Colombia is seeing progress being achieved. Driving work for the second tube of the Tunel de Occidente project has been completed, some two months ahead of schedule.

Around 497,400m3 of material has been removed from the tunnel drives since excavation commenced in September 2018. The Tunel de Occidente features twin parallel tubes, each with a length of 4.6km. The tunnel forms part of the Autopista al Mar 1 road project, linking Medellin with Santa Fe.

The tunnel is being built by the concessionaire Desarrollo Vial al Mar (Devimar).

Related Content

  • Doha’s massive ring road expressway project
    July 10, 2019
    The huge Doha ring road project will help decongest the city and improve transport for Qatar
  • Colombia’s La Linea Tunnel completion in sight
    May 7, 2015
    The completion of Colombia’s long-running La Linea Tunnel project is now in sight, finally. Colombia’s president, Juan Manuel Santos, and vice president, German Vargas Lleras, made a joint announcement that the 8.65km long tunnel will be inaugurated in November 2016. The two tunnel drives (from Quindio and Tolima) have now met in the middle and only lining works are left to be completed. Once the tunnel is operational, it will enable trucks to complete the journey between Cajamarca (Tolima) and Calarca (Qui
  • New bridge being completed in Colombia
    January 19, 2016
    A key bridge link is due for completion in Colombia shortly. The new Moravia bridge forms part of the Santa Madre Laura road project and should be complete in April 2016. The bridge is over 500m long and has cost some US$46.8 million to build. The work is being carried out by construction consortium Bermejal. Once open to traffic the bridge will help to reduce traffic on the existing Barranquilla and Mico bridges by providing an alternative route to west Medellin.
  • Colombia bridges for redesign and repairs
    October 12, 2020
    Two key Colombian bridges are to be redesigned and repaired.