Colombian tunnel project progress

A key Colombian tunnel project is seeing progress.
By MJ Woof August 31, 2020 Read time: 1 min
Progress is being seen in Colombia for the Tunel de Occidente project - image © courtesy of Wollertz, Dreamstime.com

An important road tunnel project in Colombia is seeing progress being achieved. Driving work for the second tube of the Tunel de Occidente project has been completed, some two months ahead of schedule.

Around 497,400m3 of material has been removed from the tunnel drives since excavation commenced in September 2018. The Tunel de Occidente features twin parallel tubes, each with a length of 4.6km. The tunnel forms part of the Autopista al Mar 1 road project, linking Medellin with Santa Fe.

The tunnel is being built by the concessionaire Desarrollo Vial al Mar (Devimar).

Related Content

  • Ethiopia’s new tolled highway opens
    June 21, 2019
    Ethiopia is now benefiting from a new tolled route, improving transport between Dire Dawa and Dewele.
  • Zimbabwe road upgrade being planned
    February 4, 2019
    Construction work for the Beitbridge to Victoria Falls road upgrade project is expected to start shortly.
  • Work underway on Texas highway upgrades
    August 25, 2020
    Work is well underway on key Texas highway upgrade projects.
  • Denmark’s Roskilde Bridge officially opened
    October 1, 2019
    The official opening of Denmark’s new Roskilde Bridge has been carried out. The structure has been named Crown Princess Mary´s Bridge. The 1.3km structure is the first cantilevered bridge to be built in Denmark since 1970. Construction took 36 months and the work was completed three months ahead of schedule. The project posed some challenges to the engineers and designers as the construction work was subject to environmental restrictions. Because it lies close to a residential area and a summerhouse area,