Colombian tunnel project faces further delays

The Colombian Government is looking to cancel the contract for the construction of the La Linea tunnel. This project has already been beset by an array of problems since it was first conceived and now looks set to be further delayed. Work was supposed to have been 20% complete by March 2014, however a series of delays had put the project far behind schedule and by March 2014, only 12% of the work had been carried out. In June 2014, the project was supposed to be 50% complete, but work was in fact just 14% h
September 16, 2014 Read time: 2 mins
The Colombian Government is looking to cancel the contract for the construction of the La Linea tunnel. This project has already been beset by an array of problems since it was first conceived and now looks set to be further delayed. Work was supposed to have been 20% complete by March 2014, however a series of delays had put the project far behind schedule and by March 2014, only 12% of the work had been carried out. In June 2014, the project was supposed to be 50% complete, but work was in fact just 14% had been carried out. A report by Consorcio DIS-EDL highlighted that the key objectives and deadlines for the project would not be met. The project is regarded as a priority in terms of national road infrastructure and the Colombian Government has paid 98% of the value of the contract already. The contract was due to expire in November 2014.

Related Content

  • Colombia’s La Linea Tunnel will be completed
    September 16, 2015
    Colombia's national road institute (Invias) has said that the La Linea tunnel project will open to traffic in 2017. The project has been delayed on several occasions and due to a variety of reasons, presenting a luckless and lengthy tale of woe for Colombia’s transport ministry. Early in its lifetime the project was held back by unexpected geological issues arising from more challenging ground conditions than had been initially realised. The project was also delayed by insurance problems for some of the fir
  • Colombia’s tunnel of woe faces further setback
    May 19, 2017
    The troubled tunnel construction project in Colombia to build the La Linea link has faced yet a further setback in its long tale of woe. The tender for the completion of the final 12% of the tunnel project has not managed to attract any interest from contractors. The budget for this work is an estimated US$77 million. A new tender process is being launched, with a submission deadline of 6th June 2017 and planned winner announcement on 4th July 2017. The contractor that had been building the tunnel failed to
  • Plan to complete Colombian tunnel project
    December 1, 2014
    In Colombia plans are underway to try and revive the project to construct the La Linea tunnel. The project has been beset with problems since work commenced. Problems have included insufficient funding, unexpectedly poor ground conditions and some firms involved having the wrong kind of insurance. The Segundo Centenario consortium is building the La Linea tunnel and is keen for this to continue. The new plan involves the incorporation of local firm Construcciones e Inversiones Beta, which would acquire a 40
  • Colombia road project targets may not be met
    October 10, 2017
    The ambitious road development programme set out by the Colombian Government may not meet all of its targets. The National Development Plan of 2014-2018 has set out plans for the completion of key road and highway connections, including several bridge and tunnel links. However, Colombia's National Infrastructure Agency (ANI) has so far attained 50% of the targets set out in its road development programme for the period.