Colombia tunnel building work

Excavation work will be complete on a new tunnel stretch in Colombia in Q3 2020.
By MJ Woof May 27, 2020 Read time: 1 min
Work is progressing on Colombia’s Occident Tunnel project - image © courtesy of Wollertz, Dreamstime.com

Driving work will be complete for the second Occident Tunnel section in Colombia during October 2020.

The link forms part of the highway route connecting the city of Medellin with Santa Fe and Uraba. In all, the tunnel will measure 4.6km when it has been bored, with more than 3.6km having already been driven.

The new Autopista al Mar 1 road, including the Occident Tunnel, should be complete by 2022. The project is being managed by Colombia's national infrastructure agency (ANI) and forms part of the country’s road development programme.

Related Content

  • Colombia’s mega road project auction
    November 29, 2013
    Colombia's national transport infrastructure agency ANI will auction 13 road projects with a combined value of more than US$7.87 billion (COP 15 trillion) in H1 2014, out of 40 planned. Nine of the scheduled auction projects have gone through the pre-qualification stage and will be definitely awarded in the first quarter of next year. In total, all 40 projects will involve investments of COP 47tn. The plan is to improve 8,000km of roads in the country. Four projects will be put through pre-qualification s
  • Colombia tunnel construction cost climbs
    January 25, 2018
    Work on the La Linea Tunnel project in Colombia has cost considerably more than first anticipated. The National Road Institute (Invias) says that the bill so far tops US$774 million. Extra costs of around $281.5 million have been incurred due to the need to drive a pilot tunnel as well as for three additional tunnel stretches as well as bridges along the approaches to the main tunnel. The project is now expected to be complete by the end of 2018, somewhat later than originally expected.
  • Poland bidders angry over Astaldi win for Warsaw Ring Road work
    June 18, 2015
    Four groups that made bids for building the southern section of the Warsaw Ring Road have filed complaints about how the national road authority GDDKiA chose Astaldi as the winner. Companies appealing to the National Board of Appeal (KIO) are Impresa Pizzarotti, Porr Polska, Salini Polska and IDS-BUD. The offer made by Italian company Astaldi was at least 25% less than the estimated €391 million cost of the project, according to Polish media reports. World Highways reported in February that Astaldi
  • Russia's key highway development project
    February 8, 2012
    One of the largest construction programmes in Europe is being carried out to get a Russian resort ready for the Winter Olympics. Patrick Smith reports