Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Colombia road project tender process
    July 22, 2019
    The tender process for Colombia’s Buga-Buenaventura fourth generation (4G) toll road project is being planned. The tender for the 114.1km dual carriageway is being handled in two separate stretches however. One of the road stretches will be for a 55.4km section from Buga to Loboguerrero, which is expected to cost US$359.45 million. The 58.7km stretch from Loboguerrero to Buenaventura meanwhile is expected to cost $362.75 million. The Loboguerrero to Buenaventura section of the route includes building a 19km
  • Award winning bridge for North Carolina
    November 21, 2019
    A new bridge in the US state of North Carolina has won a key award for excellence – Mike Woof writes
  • Chile-Argentina tunnel project moving ahead
    June 26, 2014
    So far 18 companies have been registered as eligible for tenders in the Agua Negra Tunnel project, which will link Argentina with Chile. The tender process is commencing for the project in the second half of 2014. The new tunnel will provide a better alternative to existing routes connecting the two countries through the Andes Mountain range at present. One of the existing routes is through a high mountain pass, which is frequently blocked due to poor weather while being unsuitable for heavy vehicles. The o
  • Chile-Argentina tunnel project moving ahead
    June 26, 2014
    So far 18 companies have been registered as eligible for tenders in the Agua Negra Tunnel project, which will link Argentina with Chile. The tender process is commencing for the project in the second half of 2014. The new tunnel will provide a better alternative to existing routes connecting the two countries through the Andes Mountain range at present. One of the existing routes is through a high mountain pass, which is frequently blocked due to poor weather while being unsuitable for heavy vehicles. The o