Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Ground penetrating radar used to investigate tunnel deterioration
    May 13, 2015
    Using ground penetrating radar to determine reason for serious pavement settling in Kentucky-Tennessee tunnel Just a few years after the opening of the Cumberland Gap Tunnel, highway officials noticed moderate to severe settling of the continuously reinforced concrete pavement. The mountain tunnel provides an important link between Kentucky and Tennessee along US25E and the problem looked serious, with many voids discovered beneath the pavement surface. To investigate the problems, the Kentucky Transpor
  • US road safety is a cause for concern
    September 6, 2021
    There is concern over a worrying trend in US road safety, while there have been steady gains in road safety in Europe
  • Paving a tunnel at altitude
    September 3, 2021
    A road tunnel stretch that opened for traffic in India in late 2020 is notable for several reasons. The new 9km Atal Tunnel is the world’s longest tunnel at an altitude of higher than 3,048m
  • Guatemala’s new bridge will cut traffic delays
    November 22, 2023
    Guatemala’s new bridge will cut congestion and traffic delays.