Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Contractors competing Colombian construction concessions
    May 13, 2014
    The tender process is underway for the third section of Colombia’s Pacific route connecting La Pintada and La Felisa. This route forms part of the Autopistas de la Prosperidad project between Medellin and Buenaventura. The 231km section includes 26 bridges and three tunnels and will cost some US$621.4 million to construct. All three sections plus the Magdalena and Norte highway will be awarded by July 2014 with works due to begin in 2015. The highway stretches should all be finished in 2020. For the first s
  • Work underway on key Romanian projects
    March 28, 2022
    Work is well underway on key Romanian road and bridge projects.
  • Bidding for Uganda road connecting Kampala and Jinja
    May 22, 2018
    In Uganda bidding is now underway for the new expressway project to improve transport between capital Kampala and the industrial city of Jinja. The project for the 95km section of road is expected to cost US$1 billion to construct. The contract is being offered under the design, finance, build and operate model, with the route then being handed back to the Ugandan Government once the agreed concession period is complete. Some of the financing will be provided by the Africa Development Bank (AfDB), French De
  • Bridge of international accord from Russia-China
    May 29, 2018
    A new bridge project joining China and Russia is a sign of international accord between the two nations – Mike Woof writes A new bridge spanning what China calls the Heilongjiang River and which is known as the Amur River in Russia, is a clear sign of an important international accord between the two countries. Discussions over the bridge project were first started between China and Russia in the 1980s, with both nations seeing many changes in leadership since that time. But while the political discussion