Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Colombia’s longest bridge – on track for completion
    March 23, 2018
    Colombia’s longest bridge is on track for completion shortly. The 4.7km-long bridge provides a connection over the Cienaga de la Virgen wetland area. The new bridge forms part of the dual carriageway road link between Cartagena and Barranquilla. When complete, it will also be the third longest bridge in Latin America. The project has been complex due to the environmentally sensitive nature of the area where it is being built. To minimise impact the builders have used pre-fabricated components and assembled
  • Colombia infrastructure expansion plan underway
    August 22, 2017
    Colombia is moving ahead steadily with its 4G road development scheme. According to the Colombian Chamber of Infrastructure (CCI), the Colombian Government has awarded 31 of the 4G projects to date. And of these 31 projects, 21 are being built at present with another eight in the process of securing financing. In all these 21 active projects and the eight close to commencement are worth a total of US$4.37 billion. The Colombian Government hopes that financing will be secured for a further two projects by th
  • Mumbai’s new coastal transport link
    July 6, 2022
    Mumbai’s new coastal road presents an ambitious and challenging project that will help improve the lives of the city’s inhabitants - Mike Woof writes
  • Brazil highway concessions in renegotiation
    October 25, 2017
    Two firms holding concessions for major highways in Brazil are asking the government for the terms to be renegotiated. Odebrecht Transport and Triunfo Participacoes e Investimentos are looking to join a new concession renegotiation scheme.