Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Cameroon key contract construction continues
    March 10, 2020
    Construction work on a key contract in Cameroon is continuing.
  • Progress for Stonehenge Tunnel bypass project
    April 6, 2020
    Progress is being seen with the planned Stonehenge Tunnel bypass project.
  • Third phase for Colombia’s complex PPP project
    September 15, 2017
    Work is underway on the third stage of Colombia’s Bogota-Villavicencio road project. This 24km project is being carried out under the PPP model by the concession holder, Concesionaria Vial Andina (Coviandina). The project is complex and includes the construction of seven tunnels in all, which have a total length of 10.7km, as well as 21 bridges and overpasses measuring 3.8km in all. Coviandina has bored around 930m of the total tunnel length at present.
  • Tunnel project for south German town to restart
    August 5, 2019
    Construction work is to restart on a new tunnel project in the South German town of Garmisch-Partenkirchen following the necessary approvals having been received. The town lies to the south of Munich and is a popular winter ski resort, while in summer it also experiences heavy tourist traffic as it lies on a key route between Germany and Austria, as well as Italy, lying to the south. The busy Autobahn 95 connects Munich’s southern side with Garmisch-Partenkirchen. But this route ends just to the northern si