Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Tunnel inspections reveal safety compliance need
    May 9, 2012
    Results show the state of Europe's tunnel infrastructure at its 'most sublime and most depressing quality' as Patrick Smith reports. EuroTAP [European Tunnel Assessment Programme] 2010 has unveiled the results of inspections conducted earlier this year in 26 major tunnels in 13 European countries. The on site inspections, carried out between 12 April and 20 May, 2010, are said to indicate that an "alarming number of operational tunnels across Europe will not be ready to comply with EU tunnel safety rules wh
  • Plans in hand for Slovakia’s longest tunnel
    June 16, 2014
    In Slovakia plans are being made for a new project that will become the country’s longest tunnel when it is complete. Salini Impregilo is the contractor heading the project. The work looks set to cost in the order of €410 million and the project is due for completion in late 2019 or early 2020. Although there was a lower priced bid for the project, this was excluded due to technical problems relating to the proposed tunnel exits. The Visnove Tunnel will measure some 7.7km long and will be constructed in the
  • Scotland’s Queensferry Crossing to open in summer 2017?
    May 31, 2017
    If good weather conditions continue then Scotland’s new Queensferry Crossing should open to traffic between July and August of this year. The bridge had originally been intended to be ready by December 2016 but construction work was delayed due to tough weather conditions.
  • Speed and precision make for perfect tunnelling combination
    May 21, 2014
    Speed and precision have been the hallmarks of a number of major road tunnelling projects across the globe over the last 12 months, as the latest sector equipment from leading manufacturers has found itself in high demand. Guy Woodford reports Herrenknecht tunnel boring machines (TBM) have been busy tunnelling under major Chinese rivers, demonstrating phenomenal speed, top safety levels and extreme precision while playing a key role in the construction of road tunnels in the Yangtze River Delta. The Yang