Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Solution found for Colombian tunnel project?
    March 12, 2015
    A solution seems to have been found for Colombia’s long-running La Linea Tunnel project. Work has been delayed on the tunnel for a number of reasons and on a number of occasions, most recently due to funding issues. But previous delays were due to such diverse causes as technical challenges posed by the difficult conditions and a lack of suitable insurance cover. The Colombian Government has come to an agreement with the Segundo Centenario consortium building the tunnel that will see construction activity r
  • Colombia tunnel project conclusion plan
    December 6, 2016
    Tendering is commencing for the final portion of works to complete Colombia’s La Linea tunnel project. Around 12% of the work on the tunnel still has to be completed, with the work expected to cost US$68.5 million. The tender is being carried out by Colombia's National Road Institute (Invias). The tunnel project has been delayed for a series of reasons. Colombian contractor Constructora Carlos Collins was constructing the tunnel but did not meet the necessary deadline. As a result, Invias opted to open the
  • Key Colombia tunnel projects delayed
    September 21, 2018
    Construction work on Colombia’s two key tunnel projects is being delayed, with insufficient funding proving a major challenge. Both the Toyo Tunnel and La Linea Tunnel projects are behind schedule. In addition, the project to construct the Pumajero Bridge is also being delayed due to a lack of funds.Part of the problems is that the designs for these projects have been revised as construction work has progressed. However the additional funds to pay for the new design features added have not been fully
  • Three Colombian bridge projects commencing
    January 17, 2019
    In Colombia progress is being seen on three major bridge projects located in different parts of the country. Construction of the new Pumajero Bridge is well in hand and is expected to be complete before the end of 2019. The new PumajeroBbridge will be 2,247m in length and have 990m of viaduct connections and access, as well as two three-lane carriageways on each side. Once the new bridge is open to traffic, the old cable-stayed concrete link between Baranquilla and Sitionuevo will be demolished. The new