Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Moscow to turn from implementation of Fourth Ring Road project
    January 5, 2016
    The Moscow City Government plans to complete building of the North-East and North-West Chords, two of the biggest road building projects in the city for the last 15 years The links will be completed during the next several months, according to an official spokesman of the Moscow Government. Both roads are considered as a cheaper alternative to the Fourth Ring Road, the construction of which was considered by the Moscow Government several years ago. However due to huge costs, which are estimated at mo
  • Improving tunneling method selection
    December 11, 2015
    The tunnelling sector remains one of the most active segments of the construction industry worldwide, fuelling demand for equipment However, there have been issues with the efficiency of the selection process for the most suitable tunnelling method for a project in the past. With this in mind, the Italian hydraulic breaker manufacturer Indeco has been working on a new algorithm that allows a contractor to optimise the tunnelling method selection. The firm said that this system has been developed becau
  • Plans in hand for Colombian highway project
    December 5, 2013
    The Colombian authorities have plans in hand for a US$240 million highway upgrade project. In all, 10 groups have been pre-selected for the tender process for the work, according to a report by Business News Americas. The project is for upgrades and improvements to a 173km stretch of the Puerta de Hierro-Cruz del Viso highway. This work includes improvements to access roads in the area, which lies in Colombia’s northern Sucre, Bolívar and Atlántico departments. The country’s infrastructure agency, ANI, has
  • Colombia contract for construction consortium
    December 15, 2016
    Construction work to widen the Autopista Norte highway in Colombia is being handled by the Accenorte consortium. The work involves widening a 4.2km stretch of the highway, which lies to the north of Colombia’s capital Bogota. The project is worth close to US$157 million, with the majority of the funding being delivered by the consortium partners and the remainder from a Colombian Bank. The consortium is led by Mincivil with a 57.43% stake. It also includes Universal with a 16.7% share, Castro Tcherassi with