Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Colombia’s Tunel de Oriente delay
    August 20, 2018
    The construction of Colombia’s Tunel de Oriente project is running behind schedule. Unexpected geological problems are the reason for the delay to the project’s completion. However the builders have assured the client that the delay will not increase the cost of the project. The tunnel, located in Colombia’s Antioquia Department, was due for completion in December 2018 but will now be ready by May 2019.
  • Breakthrough for Slovenian Karavanke Tunnel
    April 2, 2024
    The existing tunnel Karavanke Tunnel tube between Austria and Slovenia opened in 1991.
  • Russian roads and bridges being planned
    April 22, 2020
    Russian road and bridge construction and maintenance works are being planned.
  • Colombian tunnel project to open for tender
    May 4, 2012
    Colombia's Transport Ministry has announced that the contract for the second La Linea tunnel will be put out to tender before the end of 2011. The contract will be one of a number of infrastructure projects worth a total of US$2.41 billion, which will be put out to tender soon. Most of the contracts planned for tendering are for road projects. Colombia has been investing heavily in upgrading its infrastructure in a bid to develop the country's economy by boosting its transport connections.