Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Yunex tunnel management in Israel
    November 29, 2022
    The new Route 16 opens another gateway to Jerusalem and connects Highway 1 with the western and southern neighbourhoods
  • Province halts planned Vancouver bridge to replace Massey Tunnel
    September 14, 2017
    Canada’s province of British Columbia has stopped procurement for a proposed 10-lane US$2.8 billion bridge to replace the ageing George Massey Tunnel near Vancouver. Local media said the province would pay $1.65 million to two of the three shortlisted consortia which had already submitted bids for what is officially called the George Massey Tunnel Replacement project.
  • Province halts planned Vancouver bridge to replace Massey Tunnel
    September 14, 2017
    Canada’s province of British Columbia has stopped procurement for a proposed 10-lane US$2.8 billion bridge to replace the ageing George Massey Tunnel near Vancouver. Local media said the province would pay $1.65 million to two of the three shortlisted consortia which had already submitted bids for what is officially called the George Massey Tunnel Replacement project.
  • Polish projects provide transport plan
    September 19, 2014
    Poland is planning to enter seven transport projects to the Connecting Europe Programme, with these having a combined value close to €2.86 billion. Among the planned projects are the S61 express road between the Lithuanian border and Augustow. Meanwhile STRABAG and Budimex have formed a consortium that will construct a 41km stretch of the A4 highway in Poland. The section of the route runs from Rzeszów to Jarosław, in south-eastern Poland. The project is expected to take 14 months to complete and the contra