Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Developments in minimising construction defects
    February 27, 2012
    Egis has an innovative approach to addressing construction defects - *Martin O’Flaherty, Jean Pohu. Defects often become apparent after construction projects are handed over to the client and this is a common problem across most highway projects. The problem is shared by highway operators who have assumed the responsibility of managing such projects.
  • Bosnia cancels a tender for Corridor 5C, part of European route E73
    March 13, 2017
    Bosnia is cancelling a tender for part of its Corridor 5C project, an integral part of the class-A north-south central European route E73. Route E73 runs around 700km from Hungary south through eastern Croatia to Bosnia and Herzegovina and the Adriatic Sea in the area of Ploče port. The longest part of this corridor goes through Bosnia and Herzegovina – nearly 340km. Director of the Bosnian motorways company Autoput FBiH, Adnan Terzic, confirmed the cancelled tender to the Bosnian daily newspaper Dnev
  • Vietnam tunnel project faces delays
    July 20, 2018
    The expansion work for the Hai Van 2 Tunnel project in Vietnam now looks to face delays. A dispute over land compensation by residents in the area is holding back progress. Around 38% of the work for the Hai Van Tunnel 2 project was supposed to have been finished by July 2018 but in fact, only 25% of the work has been carried out.
  • Building Egypt's world class Desert Highway
    February 9, 2012
    A huge highway upgrade project will transform the Cairo-Alexandria road link into a world-class connection as Mike Woof reports