Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Colombian highway costs spiral
    February 15, 2012
    Cost increases are affecting a major highway project in Colombia.
  • Costa Rica highways projects planned
    December 1, 2017
    Costa Rica’s long running San Ramon road project is costing more than originally expected while taking longer to build than planned. The work on the 30km stretch of road was planned initially to cost US$185 million but has so far cost $287.4 million. Meanwhile only around 86% of the project has actually been carried out, despite the work already having been underway for 12 years. Costa Rica’s national road authority, Consejo Nacional de Vialidad (Conavi) is in discussions with contractor Sanchez Carvajal
  • High demand for German-made construction machinery
    February 14, 2018
    The German construction equipment industry is in the middle of a boom, according to data from the country’s equipment manufacturing body, the VDMA. A new report highlights that turnover and incoming orders saw a double-digit increase in 2017 and Germany manufacturers are starting 2018 with a high degree of optimism. According to the VDMA figures, the German construction equipment industry ended 2017 with turnover of €10.8 billion– an increase of 15% compared to the previous year. It is the fourth
  • Central Asia’s need for improved transport infrastructure
    October 5, 2018
    Central Asia has a need for improved transport infrastructure to help develop economies - Gordon Feller reports