Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Vinci picks up Lafonataine Tunnel work
    August 12, 2020
    The renovated tunnel is expected to have about 40 years of life.
  • More EU money for Fehmarn Belt Link
    July 4, 2022
    The money underlines the importance of the 17.6km Fehmarnbelt tunnel project for the entire European road network.
  • Moscow to invest $20 billion in massive road-building by 2015
    March 28, 2014
    A huge investment in road building will expand Moscow’s network – Eugene Gerden reports The government of Moscow plans to invest more than RUB 640 billion (US$20 billion) during the period of 2014-2015 .in a massive investment of road building in the city. This is expected to be part of Moscow city’s Master Plan, which is designed until 2025. Building of new roads is crucial for Moscow and should help the city to solve the problem of traffic jams. Despite all the efforts made by the city’s authorities in re
  • Czech tunnel delays
    March 6, 2012
    Progress is being made in the Czech Republic on two key urban tunnel projects. In capital Prague, the Czech contractor Metrostave has now completed the drilling portion of the Letna section of the Blanka road tunnel. Local residents have complained about the noise, vibration and cracks in their properties that they say have been generated by the drilling and blasting work. The project looks as though its completion date will be later than first planned however.