Colombia continues tunnel plans

With work on Colombia's first La Linea tunnel still incomplete, discussions are now being held regarding plans for the second tunnel.
February 17, 2012 Read time: 1 min
With work on Colombia's first La Linea tunnel still incomplete, discussions are now being held regarding plans for the second tunnel. The country's roads administration body, 2812 Invias, estimates the second tunnel as being likely to cost US$407 million to construct. Work on the second link is planned to start in the next four years, although given the track record of the first tunnel, the project could take considerably longer. The first La Linea tunnel project has been hit by a series of serious delays including the discovery that the geology of the route was considerably worse than expected, requiring a major redesign, and a stoppage stemming from insurance problems. When complete the first tunnel will link Bogota with Buenaventura and the second tunnel will further boost capacity on the route. At present there is heavy congestion on the existing links between the two cities and journey times are long, while there are also concerns over safety for road users. Meanwhile Invias is planning other road projects including 207km of roads between Bogota and Buenaventura, with a total estimated cost of $945 million. A further $1.4 billion will be invested on the new highway linking Bogota with Cucuta.

For more information on companies in this article

Related Content

  • Interest strong for Colombia key tunnel project
    January 22, 2019
    Interest is strong in the project to complete Colombia’s key tunnel construction contract. In all 23 firms have shown interest in the package of works to complete the La Linea tunnel project, according to the Colombian national road institute (Invias). The Colombian Government is providing US$204.5 million to complete the project. The current target is for the tunnel to be completed by 2020, although the link was originally supposed to be ready for traffic in late 2016. Construction work on the link commenc
  • Colombia tunnel construction cost climbs
    January 25, 2018
    Work on the La Linea Tunnel project in Colombia has cost considerably more than first anticipated. The National Road Institute (Invias) says that the bill so far tops US$774 million. Extra costs of around $281.5 million have been incurred due to the need to drive a pilot tunnel as well as for three additional tunnel stretches as well as bridges along the approaches to the main tunnel. The project is now expected to be complete by the end of 2018, somewhat later than originally expected.
  • Colombia’s troubled tunnel project completion due
    April 26, 2017
    The completion of work on Colombia’s troubled tunnel project is now finally in sight. A new contractor will be selected by Colombia's National Road Institute (Invias) to complete the last section of work required on the La Linea Tunnel. The winner of the tender process will be announced on 13th June 2017. An additional US$50 million is being budgeted by the Colombian authorities to complete the work. It is expected that in all, finishing the project will cost $86.6 million. Work still to be carried out incl
  • Colombia tunnel delays continue
    September 26, 2016
    Further delays have hit the project to build the La Linea Road Tunnel in Colombia. As a result the tunnel will not be open to traffic until the first half of 2018. This is the latest in a series of delays that have held back the opening of the tunnel. Previous delays have been caused by the discovery of geological conditions that were far more challenging than originally expected as well as problems over insurance cover for the construction firms. When open to traffic the new link will stretch 8.6km and wil