Cleveland Bridge on A1 project in the UK

Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges. Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge. The work was carried out on behalf of Highways England’s principal contractor on the A1 scheme, a Carillion and Morgan Sindall joint venture. The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorw
February 7, 2017 Read time: 2 mins
Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges.

Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge.

The work was carried out on behalf of 8100 Highways England’s principal contractor on the A1 scheme, a 2435 Carillion and 2567 Morgan Sindall joint venture.

The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorway. As part of the extensive civil engineering works, the project required a collection of new bridges and extensions to existing structures to accommodate the larger motorway.

From its extensive facility in Darlington, Cleveland fabricated and provided protective treatments to the steel work for the bridges, allowing the newly widened A1 to span existing roads and rivers or carry access roads over the new highway.

The company also undertook the erection and installation of the bridges, which range between 80-400 tonnes. This included the scheme’s largest bridge, the 86.5m-long and 398tonne Kneeton Lane Bridge, near Scotch Corner.

Cleveland also supported the widening of existing structures, most notably the Agricola Bridge. This required an additional 170tonnes of steel to widen the bridge by 7m either side and to a span of 57m.

“This was a highly time-focused project involving the production and installation of around 1,600 tonnes of steel,” said Chris Droogan, managing director of Cleveland Bridge UK. “Working closely with our client we have efficiently completed the delivery of the bridges, which is a significant milestone in this major civil engineering project.”

For more information on companies in this article

Related Content

  • Geosynthetics stabilise differential settlement
    March 14, 2012
    The ongoing Highways Agency A66 Carkin Moor to Scotch Corner project involves upgrading the original single carriageway to address safety concerns, particularly at junctions and crossings. Where differential settlement is threatening a remodelled junction, Tensar International's new TriAx geogrid provides an additional dimension of stability, saving design and build contractors Balfour Beatty Regional Civil Engineering Limited (BBRCEL) the heavy time and costs inherent in conventional remedial solutions and
  • Modern formwork systems - fast, flexible, safe
    February 21, 2012
    Speed of erection, safety, cost-efficiency and flexibility are among the attributes of modern formwork systems. Modern formwork and scaffolding systems are attractive in particular for their speed of erection, safety, cost-efficiency and flexibility.
  • Major Danish project for Atkins
    March 1, 2012
    Engineering firm Atkins is now handling design work on a major highway and bridge project in Denmark.
  • Peri cantilever for Terfener Bridge
    February 26, 2021
    Peri used its VBC Balanced Cantilever Carriage for the first time in Central Europe.