Champlain Bridge set to open by end of year, says SNC-Lavalin

The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
March 6, 2018 Read time: 2 mins
Montreal’s Champlain Bridge: on schedule, so far, with 65% complete and opening set for December (photo courtesy Signature sur le Saint-Laurent Construction S.E.N.C.)
The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project.


Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are 981 Hochtief, 2758 Flatiron, 4761 Dragados Canada and Grupo 917 ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, will have the six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the île des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.
 
The new composite girder bridge across the river and Seaway consists of a 170m-high twin-tower cable stay bridge with a front span of around 240m and a back span of 120m.

Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km. Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US.

For more information on companies in this article

Related Content

  • A key Canadian road project is being investigated
    May 16, 2012
    An investigation is underway in Canada concerning the Bonaventure Expressway upgrade project. Canadian firm Societe du Havre (SHM) is being investigated by Montreal's authorities. The first phase of the reconstruction work is worth US$141.4 million (C$141.7 million). The road project is currently being controlled by both SHM and the city through a project office. The authorities are questioning the need to have two joint managers for the project. SHM will submit its financial statements for 2011/2012 to the
  • UK’s Silvertown Tunnel project facing legal dispute
    August 22, 2019
    A legal battle is facing the UK’s Silvertown Tunnel project. A consortium called STC and comprising Dragados and Hochtief is presenting a legal case over the project. According to STC, there are issues over the way in which the preferred bidder for the work has been selected. The work is for a new tunnel under the River Thames in the east of London. The project is expected to cost £1 billion. The Riverlinx consortium is currently the preferred bidder. Building the tunnel will help reduce congestion. The
  • LagoonHull still on the cards
    February 7, 2022
    A proposed major river development in Hull would include an immersed road tunnel to connect traffic arriving from Europe with the UK’s motorway network.
  • Virginia tunnel project seeing advance
    July 19, 2023
    Virginia’s massive tunnel project is seeing advance.