Champlain Bridge set to open by end of year, says SNC-Lavalin

The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
March 6, 2018 Read time: 2 mins
Montreal’s Champlain Bridge: on schedule, so far, with 65% complete and opening set for December (photo courtesy Signature sur le Saint-Laurent Construction S.E.N.C.)
The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project.


Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are 981 Hochtief, 2758 Flatiron, 4761 Dragados Canada and Grupo 917 ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, will have the six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the île des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.
 
The new composite girder bridge across the river and Seaway consists of a 170m-high twin-tower cable stay bridge with a front span of around 240m and a back span of 120m.

Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km. Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US.

For more information on companies in this article

Related Content

  • Mersey Gateway: Consortia Talks
    April 4, 2012
    The competitive dialogue phase of the Mersey Gateway Project has begun. The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months. The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013. The value of the construction phase of the project, including land, is estimated at US$961milli
  • New bridge link for Sri Lanka
    January 10, 2017
    A new bridge spanning Sri Lanka’s Mahaweli River and close to the city of Kandy has been officially opened. The bridge link connects the neighbouring villages of Dodanwala and Halloluwa in Sri Lanka’s Central Province and was opened by Maithripala Sirisena, the country’s president. The bridge is nearly 105m long and replaces a 75 year old suspension bridge that was no longer fit for purpose. The old structure carried pedestrian traffic only while the new bridge carries two lanes of vehicle traffic, as well
  • Ontario’s Highway 407 East Phase 2B extension opens
    January 23, 2020
    The 23km final extension phase of the provincially-owned tolled freeway Highway 407 East near Toronto, Canada has opened.
  • Bold move aids Ironton-Russell bridge works in U.S.
    January 24, 2014
    The bold decision to go against the norm and build the back spans using falsework for the Ironton-Russell replacement bridge between Parkersburg, Kentucky and Cincinnati, Ohio allowed land access to build the main span which, along with the first use in the U.S. of precast stay anchor blocks, meant the new structure could get built.