Champlain Bridge set to open by end of year, says SNC-Lavalin

The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
March 6, 2018 Read time: 2 mins
Montreal’s Champlain Bridge: on schedule, so far, with 65% complete and opening set for December (photo courtesy Signature sur le Saint-Laurent Construction S.E.N.C.)
The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project.


Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are 981 Hochtief, 2758 Flatiron, 4761 Dragados Canada and Grupo 917 ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, will have the six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the île des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.
 
The new composite girder bridge across the river and Seaway consists of a 170m-high twin-tower cable stay bridge with a front span of around 240m and a back span of 120m.

Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km. Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US.

For more information on companies in this article

Related Content

  • Kenya port suspension bridge project makes progress
    January 15, 2019
    A new suspension bridge in Kenya’s key port city, Mombasa, will help unlock potential – Shem Oirere reports Plans for the construction of a US$200 million suspension bridge in Kenya heva moved a notch higher. The country's urban roads agency recently announced the shortlisting of three bidders for the design, finance, construct, operate, maintain and transfer public private partnership (PPP) contract model. Kenya Urban Roads Authority (KURA) is a state agency that manages, develops, rehabilitates and mai
  • Major highway widening project in Netherlands
    December 15, 2014
    A major highway widening and upgrade project is being carried out in the Netherlands in a bid to improve traffic flow on some of Europe’s busiest routes. SAAone is carrying out the work for the A1-A6 motorway project for Rijkswaterstaat, the Dutch Directorate-General for Public Works and Water Management. A key component of the project is adding new lanes to the A1 and A6 highways.
  • Gordie Howe Bridge towers rise
    January 19, 2022
    Each tower is composed of 51 segments constructed using a jump-form climbing system.
  • British Columbia issues RFQ for US$2.7 billion Massey Bridge
    June 30, 2016
    Canada’s provincial British Columbia government has issued a request for qualification for construction of a US$2.7 billion bridge over the Fraser River around the city of Vancouver. The 10-lane bridge will be built under a 30-year public-private partnership agreement and will include tolled transit lanes and related Highway 99 improvements between Bridgeport Road in the adjacent city of Richmond and Highway 91 in the city of Delta. The 60-year-old tunnel now carries its limit of 80,000 vehicles a day an