Champlain Bridge set to open by end of year, says SNC-Lavalin

The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
March 6, 2018 Read time: 2 mins
Montreal’s Champlain Bridge: on schedule, so far, with 65% complete and opening set for December (photo courtesy Signature sur le Saint-Laurent Construction S.E.N.C.)
The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project.


Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are 981 Hochtief, 2758 Flatiron, 4761 Dragados Canada and Grupo 917 ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, will have the six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the île des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.
 
The new composite girder bridge across the river and Seaway consists of a 170m-high twin-tower cable stay bridge with a front span of around 240m and a back span of 120m.

Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km. Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US.

For more information on companies in this article

Related Content

  • Montreal's new Champlain Bridge ready by 2018
    December 2, 2013
    Montreal’s Champlain Bridge will be replaced by 2018, according to the Canadian federal government. The government pledge is three years earlier than the original plans to replace the landmark structure. The new US$ 4.71 billion (CAD 5 billion) toll bridge is to be constructed through a public-private partnership and the procurement process is set to commence in spring 2014. Poul Ove Jensen has been selected by the government to design the replacement Champlain Bridge which, with its almost 160,000 daily
  • Fluor and ACS Infrastructure Canada win Gordie Howe Bridge deal
    July 6, 2018
    A partnership including Fluor and ACS Infrastructure has been chosen to design, build, finance, operate and maintain the Gordie Howe International Bridge project. The client, Windsor-Detroit Bridge Authority (WDBA), announced the appointment of Bridging North America group in the Canadian city of Windsor, across the Detroit River from Detroit in the US state of Michigan. The Gordie Howe International Bridge will connect the two cities by linking Interstate 75 and Interstate 96 in Michigan with the new
  • Virginia state issues RFP for $2.1 billion Interstate 66 toll expansion
    December 23, 2015
    The Virginia Department of Transportation (VDOT) has issued a draft request for proposals (RFP) for the US$2.1 billion Interstate 66 tolled expansion project. Work under a 40-50-year public-private partnership is expected to include construction of 46km of lanes.
  • Safety measures aid workzone accident reduction
    February 20, 2012
    Everyone connected with the highway industry is involved in the efforts to cut down the number of work zone accidents. Patrick Smith reports. A few months ago, as road work resumed on America's highways and bridges, US Transportation Secretary Ray LaHood called on drivers to use extra caution in work zones. At the same time he commended the success in reducing overall roadway fatalities in each of the last seven years.