Champlain Bridge set to open by end of year, says SNC-Lavalin

The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
March 6, 2018 Read time: 2 mins
Montreal’s Champlain Bridge: on schedule, so far, with 65% complete and opening set for December (photo courtesy Signature sur le Saint-Laurent Construction S.E.N.C.)
The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project.


Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are 981 Hochtief, 2758 Flatiron, 4761 Dragados Canada and Grupo 917 ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, will have the six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the île des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.
 
The new composite girder bridge across the river and Seaway consists of a 170m-high twin-tower cable stay bridge with a front span of around 240m and a back span of 120m.

Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km. Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US.

For more information on companies in this article

Related Content

  • Bosnia cancels a tender for Corridor 5C, part of European route E73
    March 13, 2017
    Bosnia is cancelling a tender for part of its Corridor 5C project, an integral part of the class-A north-south central European route E73. Route E73 runs around 700km from Hungary south through eastern Croatia to Bosnia and Herzegovina and the Adriatic Sea in the area of Ploče port. The longest part of this corridor goes through Bosnia and Herzegovina – nearly 340km. Director of the Bosnian motorways company Autoput FBiH, Adnan Terzic, confirmed the cancelled tender to the Bosnian daily newspaper Dnev
  • Argentina’s transport plan being refined
    December 1, 2017
    Argentina is refining the country’s road development plans. The programme calls for investments of US$16.7 billion for the work, which will be carried out on 7,000km of roads. The 16 projects will be run as Public-Private Partnerships. These will be split into several corridors, including Corridor A, Corridor B, Corridor C, Corridor D, Corridor E, Corridor F, Corridor G, Corridor H and Corridor I. The work is being split into three phases. The first tender process is now open and will close in April 2018.
  • Vancouver’s 10-lane bridge replacement for Massey Tunnel remain undecided
    October 23, 2015
    Construction of a 10-lane bridge to replace a congested river tunnel in Vancouver, Canada, is still on target to start in 2017, despite details remaining sketchy.

    The bridge will replace the 60-year-old George Massey Tunnel between the local cities of Richmond and Delta along the provincial Highway 99. But the cost and – importantly – whether it will be a toll bridge have not been declared by the British Columbia provincial government.
  • Funding set for Mobile Bridge and Bayway
    December 16, 2022
    US federal money and state funding has been secured for a planned replacement toll bridge across Mobile Bay on the Gulf of Mexico coast in the south-eastern state of Alabama.