Champlain Bridge set to open by end of year, says SNC-Lavalin

The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project. Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments. Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $31
March 6, 2018 Read time: 2 mins
Montreal’s Champlain Bridge: on schedule, so far, with 65% complete and opening set for December (photo courtesy Signature sur le Saint-Laurent Construction S.E.N.C.)
The replacement Champlain Bridge in Montreal will open on schedule at the end of the year, according to the SNC-Lavalin-led consortium heading the project.


Cost of the entire corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

Failure to open the bridge to vehicular traffic on time means the consortium faces stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are 981 Hochtief, 2758 Flatiron, 4761 Dragados Canada and Grupo 917 ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, will have the six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the île des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.
 
The new composite girder bridge across the river and Seaway consists of a 170m-high twin-tower cable stay bridge with a front span of around 240m and a back span of 120m.

Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km. Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US.

For more information on companies in this article

Related Content

  • Duisburg double for lift specialist Sarens
    June 5, 2024
    Heavy lift specialist Sarens overcame challenging wind and water conditions during installation of two strategic road bridges - the Oberbürgermeister Karl Lehr Brücke and the Hafenkanalbrücke - in the German city of Duisburg.
  • Italy: Astaldi takes out loan for Turkish motorway project
    June 18, 2015
    Italian civil engineering group Astaldi has underwritten a €4.5 billion (US$5 billion) loan towards the Turkish motorway project of Gebze-Orhangazi-Izmir, which is worth an overall €5.65 billion ($6.4 billion). According to the La Repubblica newspaper, the loan facility will be used to complete the 301km last stretch of the motorway and link the city of Bursa, south of the Sea of Marmara, and the Aegean port of Izmir. Part of the loan will be used to refinance stretches that are under construction for
  • Work zone safety solution on busy world highways
    December 3, 2013
    Globally renowned highway work zone safety solution manufacturers have been providing some of their latest systems to protect roadworkers and motorists on high volume traffic highways. Guy Woodford reports Versilis has provided one of its state-of-the-art work zone safety solutions during the rehabilitation of North America’s busiest highway. The Canadian road safety product innovator and manufacturer was retained by the Ministry of Transportation of Ontario (MTO) to install automated traffic control
  • Bridge project uses high performing formwork
    February 20, 2012
    Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle. The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.