The tender process is being restarted for the project to drive the Zheleznitsa Tunnel, which will form part of Bulgaria’s Struma Highway. The tunnel project is expected to cost €128 million in all to construct with the work being split into three separate lots. Two of the lots, I and III are smaller packages for the roads at either end of the project, with the most valuable tender, Lot II, being for the €99.2 million deal to construct the tunnel itself. The tender process is being managed by the Bulgarian R
October 25, 2017 Read time: 1 min
The tender process is being restarted for the project to drive the Zheleznitsa Tunnel, which will form part of Bulgaria’s Struma Highway. The tunnel project is expected to cost €128 million in all to construct with the work being split into three separate lots. Two of the lots, I and III are smaller packages for the roads at either end of the project, with the most valuable tender, Lot II, being for the €99.2 million deal to construct the tunnel itself. The tender process is being managed by the Bulgarian Road Infrastructure Agency. Two previous tenders for the tunnel project were cancelled, delaying the construction schedule.

Related Content

  • Bulgaria continues with Struma motorway, Blagoevgrad to Krupnik
    September 14, 2017
    Bulgaria has started work on a 12.6km section of Struma motorway between the southwestern towns of Blagoevgrad and Krupnik. A consortium led by Bulgarian construction company Agromah is building the section under a contract worth just over €71 million, according to the regional development ministry.
  • Bulgaria road tunnel tender recommencing
    June 20, 2017
    The tender process for a tunnel project on Bulgaria’s Struma Highway is now reopening. The project did go to tender earlier this year but has now had to be restarted following unexpected technical issues.
  • Bulgaria lets contract for Struma Motorway’s Zheleznitsa Tunnel
    February 15, 2019
    A consortium including local firms GP Group, Global Construction and Via Plan will build the 2km Zheleznitsa Tunnel, part of the Struma Motorway. The contract is worth around €97.5 million and the tunnel will be the longest in Bulgaria. The EU Cohesion Fund will co-finance the project, along with the Bulgarian government under the Operational Programme Transport and Transport Infrastructure 2014-2020. Completion is set for the end of 2023. Two previous tender processes to award the construction con
  • Bulgaria: back on track?
    July 23, 2012
    Several important Bulgarian road projects are expected to gain momentum over the coming weeks, a welcome boost for a sector that has been beset by delays in the past. In mid-September, the National Road Infrastructure Agency (NRIA) announced that it would soon be declaring new tenders for the construction of two key road projects worth a total of US$94 million (approximately €68.8 million). One section will link the south-eastern city of Kardzhali to Podkova, near the Greek border: the second will connect t