Bridge blast allows new Ohio River crossing

A 213m section of the Old Milton-Madison Bridge was recently blasted into the Ohio River in the United States to make way for a new river crossing. Workers rigged the structure with small controlled explosives and took it down shortly after 9.15am on Sunday 28 July 2013. Small explosive charges were placed at key locations on the bridge. The charges were detonated at intervals to control the direction of the fall. Pieces of the truss will be retrieved from the river, placed on barges, and taken to the shore
July 30, 2013 Read time: 1 min
A 213m section of the Old Milton-Madison Bridge was recently blasted into the Ohio River in the United States to make way for a new river crossing.

Workers rigged the structure with small controlled explosives and took it down shortly after 9.15am on Sunday 28 July 2013.

Small explosive charges were placed at key locations on the bridge. The charges were detonated at intervals to control the direction of the fall.

Pieces of the truss will be retrieved from the river, placed on barges, and taken to the shore for further dismantling and eventually sold for scrap.

Divers are said to be on call to ensure all pieces are removed.

Click on the video link to watch the Old Milton-Madison Bridge blast

Related Content

  • VIDEO: Bridge demolition jobs in CA
    November 23, 2015
    Explosive demolition techniques were used to remove a bridge structure in the US at the weekend. In California on the west coast, the removal of a pier from the old Bay Bridge structure was carried out. The explosive demolition was organised by 5246 Caltrans, with around 10tonnes of explosives being used to blast the redundant bridge pier. Protective layers of wood and steel were used to prevent debris from the massive 24.4m x 42.7m bridge pier from being thrown into the air.
  • Demolition starts on Seattle’s Alaska Way Viaduct
    June 14, 2019
    Demolition of the Alaska Way Viaduct in the northwest US city of Seattle is underway, including the filling in of a redundant road tunnel.
  • Signify to light up Massey Tunnel
    January 15, 2021
    The LED replacements in the Vancouver area tunnel are Lumec TunnelView, made by Signify.
  • Foran Equipment helps Kananaskis kayakers construct course
    April 27, 2016
    In the Canadian Rocky Mountains, there was a window of opportunity of only several days before these excavators had to be out of the Kananaskis River ahead of nearby Barrier Dam releasing its water. The provincial Alberta Whitewater Association hired local contractor Foran Equipment to bring in their equipment in to re-work the riverbed after severe flooding in June 2013 washed out the kayaking courses.