Breakthrough on Slovakia’s D1 tunnel near Zilina

Workers in Slovakia have broken through the first of two passages in a tunnel near Zilina as part of an 11km D1 highway project. Breakthrough of the second passage of the tunnel on the section Hricovske Podhradie-Lietavska Lucka will likely be in January. Around 80m are still to be bored, according to a report in the Slovak Spectator on-line newspaper. Zilina is in northwestern Slovakia, around 200km from the capital Bratislava and close to the Czech and Polish borders. Juraj Valent, head of the Na
December 12, 2016 Read time: 2 mins
Workers in Slovakia have broken through the first of two passages in a tunnel near Zilina as part of an 11km D1 highway project.

Breakthrough of the second passage of the tunnel on the section Hricovske Podhradie-Lietavska Lucka will likely be in January. Around 80m are still to be bored, according to a report in the Slovak Spectator on-line newspaper.

Zilina is in northwestern Slovakia, around 200km from the capital Bratislava and close to the Czech and Polish borders.

Juraj Valent, head of the National Highway Company (NDS), said the section with its two tunnels and 11 bridges is scheduled for completion by October 2018. Cost is around €427 million, with money coming from the central government and the European Union.

Slovakia’s D1 motorway runs from the western border with the Czech Republic to the eastern border with the Ukraine, a 100km frontier amid remote forested areas. The government has been building and renovating the route since 1985 when a cross-country route was planned in earnest. The D1 also forms part of the European routes E50, E58, E75 E571.

Related Content

  • Breakthrough near for Čebrať Tunnel
    December 17, 2021
    The 3.5km-long tunnel through Slovakia’s Čebrať Hills is part of the D1 Ružomberok bypass.
  • Delays ahead for Slovakia’s Visnove tunnel
    September 5, 2018
    Slovakia's transport ministry says the 7.5km Visnove tunnel near Zilina, part of the D1 motorway, will be delayed by two years to open in 2022. The recent announcement came as the ministry agreed to an extension to the construction permit held by Salini Impregilo for work on the twin-tube tunnel. The design-and-build contract worth about €410 million was assigned to the Salini Impregilo-led joint venture DUHA in 2014 by the National Highway Company NDS.
  • Bratislava bypass and Karpaty tunnel completion set for 2030
    June 18, 2018
    Slovakia’s national motorway company NDS expects that the Bratislava bypass on the D4 motorway together with the Karpaty tunnel will be completed around 2030. The D4 motorway is part of the trans-European transport network and will connect with the planned R7 expressway linking western and eastern Slovakia, and the existing D1 and D2 motorways”. Apart from construction works on part of the D4 motorway, another two stretches are planned on this link, including the 3.6km stretch from Devinska Nova Ves t
  • Bratislava bypass and Karpaty tunnel completion set for 2030
    June 18, 2018
    Slovakia’s national motorway company NDS expects that the Bratislava bypass on the D4 motorway together with the Karpaty tunnel will be completed around 2030. The D4 motorway is part of the trans-European transport network and will connect with the planned R7 expressway linking western and eastern Slovakia, and the existing D1 and D2 motorways”. Apart from construction works on part of the D4 motorway, another two stretches are planned on this link, including the 3.6km stretch from Devinska Nova Ves t